Below is the current timeline for completing the project.

  • Final engineering plans will be completed in April and submitted to USDA for approval. Approximately 70 property owners have not signed their easements; however the engineering plans will bypass these properties during the initial construction phase. Once sewer becomes available, the District will pursue forced connection of these properties as allowed by Indiana Code 13-26-5-2.
  • USDA approval to put the project out for bid- early June 2014
  • Construction bids and opening of bids completed by mid-July 2014
  • Monthly sewer rate determination, public hearings, and loan closing completed by mid-October 2014
  • Construction- October 2014 through June 2016